Velocity yaiku jumlah work (biasane story point) sing diselesaike tim per Sprint, dirata-rata saka Sprint-Sprint sing kacrito. Iku bantuan perkiraan, ora target performance. Panjenengan nggunakake kanggo prediksi pira sing bisa dilekaske tim kanthi realistis sa Sprint sabanjure.
Cara nggunakake
- Average the last 3-5 Sprints' completed points
- Use that range (not a single number) to forecast
- Adjust capacity for holidays, leave, support load
- Forecast a release: remaining backlog points / velocity
Tim sing rata-rata ngrampungake 30 point karo 6 wong, ilang siji kanggo liburan, rencana luwih cedhak menyang 25 kanggo Sprint kuwi.
